ASTRID2 Time Line

| Description | Date |
| Time period for Infrastructure Grant | August 2009 - February 2014 |
2009 |
|
| ASTRID extraction kicker designed | June 2009 |
| Design DC magnets for A2 | July 2009 - August 2009 |
| Design pulsed magnets and supplies for A2 | July 2009 - August 2009 |
| Design DC power supplies | July 2009 - September 2009 |
| ASTRID2 design completed | July 2009 |
| ASTRID extraction kicker ordered | August 2009 |
| Transfer beamline design completed | September 2009 |
| ASTRID2 design report review | September 2009 |
| Order DC magnets for A2 | September 2009 |
| Order pulsed magnets and supplies for A2 | September 2009 |
| Magnets and power supplies ordered | November 2009 |
| Multipole wiggler design completed | November 2009 |
| Components for transfer beamline ordered | December 2009 |
| Order DC power supplies | December 2009 |
2010 |
|
| Detailed layout of ASTRID2 vacuum system | May 2010 |
| Installation of transfer beamline | November 2010 - January 2011 |
| ASTRID extraction kicker installed | November 2010 |
| Dark period on ASTRID to commision kicker | December 2010 - January 2011 |
2011 |
|
| Multipole wiggler delivered/installed | June 2011 |
| Commissioning of transfer beamline with beam | June 2011 |
| Magnets and power supplies delivered | July 2011 |
2012 |
|
| Radiation wall completed | May 2012 |
| Commissioning of A2 with beam | May 2012 - September 2012 |
| Beam circulating in ASTRID2 | August 2012 |
| First synchrotron light from ASTRID2 | December 2012 |
| Transfer of UV1 | December 2012 - January 2013 |
2013 |
|
| Transfer of SX700/SGM1 | January 2013 - April 2013 |
| Commissioning of UV1 with beam | February 2013 - May 2013 |
| Transfer of SGM3 | February 2013 - August 2013 |
| Undulator installed in ASTRID2 | February 2013 - March 2013 |
| Commissioning of SX700 with beam | March 2013 - June 2013 |
| First user beam on 1st monochromator on ASTRID2 | April 2013 |
| Transfer of SGM2 | June 2013 - September 2013 |
| Commissioning of SGM3 with beam | August 2013 - November 2012 |
| Commissioning of SGM2 with beam | September 2013 - December 2013 |
| Last sychrotron light in ASTRID | October 2013 |
| Transfer of CD1 | November 2013 - March 2014 |
2014 |
|
| Commissioning of CD1 with beam | April 2014 - July 2014 |
| All beamlines in operation on ASTRID2 | July 2014 |