ASTRID2 Time Line


Description Date
Time period for Infrastructure Grant August 2009 - February 2013

2009

ASTRID extraction kicker designed June 2009
Design DC magnets for A2 July 2009 - August 2009
Design pulsed magnets and supplies for A2 July 2009 - August 2009
Design DC power supplies July 2009 - September 2009
ASTRID2 design completed July 2009
ASTRID extraction kicker ordered August 2009
Transfer beamline design completed September 2009
ASTRID2 design report review September 2009
Order DC magnets for A2 September 2009
Order pulsed magnets and supplies for A2 September 2009
Magnets and power supplies ordered November 2009
Multipole wiggler design completed November 2009
Components for transfer beamline ordered December 2009
Order DC power supplies December 2009

2010

Detailed layout of ASTRID2 vacuum system May 2010
Installation of transfer beamline November 2010 - January 2011
Magnets and power supplies delivered November 2010
ASTRID extraction kicker installed November 2010
Magnets and supplies for ASTRID2 delivered November 2010
Dark period on ASTRID to commision kicker December 2010 - January 2011

2011

Commissioning of transfer beamline with beam February 2011 - March 2011
Commissioning of A2 with beam March 2011 - September 2011
Synchrotron light time shared with ASTRID2 March 2011 - June 2012
Synchrotron light time shared with ASTRID March 2011 - June 2012
Transfer of SX700/SGM1 April 2011 - September 2011
Multipole wiggler delivered/installed May 2011
Transfer of SGM2 July 2011 - December 2011
Beam circulating in ASTRID2 September 2011
Commissioning of SX700/SGM1 with beam October 2011 - November 2011
First synchrotron light from ASTRID2 October 2011
Transfer of SGM3 November 2011 - April 2012
Undulator installed in ASTRID2 November 2011

2012

Commissioning of SGM2 with beam January 2012 - February 2012
First user beam on 1st monochromator on ASTRID2 March 2012
Transfer of UV1 April 2012 - September 2012
Commissioning of SGM3 with beam May 2012 - June 2012
Last sychrotron light in ASTRID June 2012
Transfer of CD1 July 2012 - December 2012
Commissioning of UV1 with beam October 2012 - November 2012

2013

Commissioning of CD1 with beam January 2013 - February 2013
All beamlines in operation on ASTRID2 March 2013

 